Australian Capital Territory Consolidated Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

BUILDING ACT 2004 - SECT 36

Period for which approvals operate

    (1)     A building approval operates until the end of the earliest of the following:

        (a)     3 years beginning on the day of its issue;

        (b)     any development period applying to the building work.

Note     A building approval ends if a further approval is issued for the same building work (see s 34).

    (2)     If the development period applying to the building work is extended, the certifier may extend the period of operation of the building approval to a day that is no later than the day the extended development period ends.

    (3)     However, subsection (2) does not authorise the extension of the period of validity of a building approval to a day that is more than 3 years after the day the approval was issued.

    (4)     To remove any doubt, a building approval, or part of the building approval, does not operate while the approval or part is suspended.

Note     A building approval, or part of the approval, may be suspended under s 53.

    (5)     In this section:

"development period" means a period within which, under another law in force in the ACT or a condition of the relevant lease, the building work must be completed.



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback