INTEGRATED PLANNING ACT 1997 - SECT 3.5.21A

3.5.21A When approval lapses if development started but not completed

(1) A condition under division 6 may require--

(a) development, or an aspect of development, to be completed within a particular time; and
(b) the payment of security under an agreement under section 3.5.34 to support the condition.

(2) Subsection (3) applies if--

(a) a condition requires assessable development, or an aspect of assessable development, to be completed within a particular time; and
(b) the assessable development, or aspect, is started but not completed within the time.

(3) The approval, to the extent it relates to the assessable development or aspect not completed, lapses.

(4) However, even though the approval has lapsed, any security paid under subsection (1)(b) may be used in a way stated by the approval, including, for example, to finish the development.