TRANSPORT INFRASTRUCTURE ACT 1994 - SECT 36

36 Notice of entry or permission to enter

(1) The person who is proposing to occupy or use land under section 35 (Temporary occupation and use of land) must—

(a) give at least 3 days written notice to the owner or occupier of the land; or
(b) obtain the written approval of the owner or occupier to the occupation or use.

(2) The notice must state—

(a) the road works to be carried out; and
(b) the use proposed to be made of the land; and
(c) details of the things proposed to be done on the land; and
(d) an approximate period when the occupation or use is expected to continue.

(3) A notice may be given under subsection (1) in relation to land even if it is proposed to resume the land for road works.

(4) After the end of 3 days after service of a notice under subsection (1), or with the agreement of the owner or occupier, the land may be entered and the road works specified in the notice carried out.

(5) If urgent remedial attention is required, subsection (1) does not apply but the person who is proposing to occupy or use the land must, if it is practicable, notify the owner or occupier of the land orally.