South Australian Consolidated Acts49—Notice of building etc to be given to Corporation
(1) Any person
intending to build, rebuild or make extensions to any house, building or
structure within a drainage area shall, at least fourteen days before
beginning to dig or lay out the foundations thereof, give to the Corporation
written notice of such intention, together with full particulars of the levels
or intended levels of the cellar or lowest floor, and of the situation or
construction of the privies, cesspits, and drains to be built, constructed, or
used in connection with the house, building or structure.
(2) No person shall
begin to build, rebuild or make extensions to any such house, building or
structure, or build or construct any such privy, cesspit, or drain, until the
particulars so required to be stated have been approved by the Corporation,
which must signify its approval or otherwise within fourteen days after
receiving the said notice.
(3) Any person failing
to deliver such notice as aforesaid, or either wholly or partially building,
rebuilding, extending or constructing or causing to be either wholly or
partially built, rebuilt, extended or constructed, any house, building,
structure, privy, cesspit, or drain, without such approval as aforesaid, shall
be liable to a penalty not exceeding five hundred dollars.