49—Notice of building etc to be given to Corporation

        (1)         Any person intending to build, rebuild or make extensions to any house, building or structure within a drainage area shall, at least fourteen days before beginning to dig or lay out the foundations thereof, give to the Corporation written notice of such intention, together with full particulars of the levels or intended levels of the cellar or lowest floor, and of the situation or construction of the privies, cesspits, and drains to be built, constructed, or used in connection with the house, building or structure.

        (2)         No person shall begin to build, rebuild or make extensions to any such house, building or structure, or build or construct any such privy, cesspit, or drain, until the particulars so required to be stated have been approved by the Corporation, which must signify its approval or otherwise within fourteen days after receiving the said notice.

        (3)         Any person failing to deliver such notice as aforesaid, or either wholly or partially building, rebuilding, extending or constructing or causing to be either wholly or partially built, rebuilt, extended or constructed, any house, building, structure, privy, cesspit, or drain, without such approval as aforesaid, shall be liable to a penalty not exceeding five hundred dollars.



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback