South Australian Consolidated RegulationsSchedule 6—Water efficiency plans
1—Preparation of water
efficiency plans
A draft water efficiency plan must be prepared and submitted to the Minister
for approval—
(a) in
the case of a new water efficiency plan—not later than the date
specified by the Minister by notice in the Gazette; or
(b) in
the case of a water efficiency plan that is to replace an expiring
plan—not later than the day on which the existing water efficiency plan
expires.
2—Contents of water efficiency plans
A draft water efficiency plan must include the following information:
(a) a
description of the current use of the water at the site;
(b) a
list of water savings measures (expressed in terms of water saved, cost
effectiveness and potential benefits) that the person submitting the plan
proposes to implement in the 5 year period following approval of the water
efficiency plan (including initial set up costs and annual costs for each
measure and time frames for implementation);
(c) any
other information required by the Minister by notice in the Gazette, or by
notice in writing given to the relevant person.