Western Australian Consolidated Acts[s. 7(4), 8(4), 9(4), 13(5), 19 and 20]
[Heading amended by No. 19 of 2010
s. 4.]
If any condition set
out in subsection (1) of section 9 is not fulfilled solely because
the builder has failed to comply with the builder’s obligations under
subsection (2) of that section, the contract is not affected but remains
in force on the same terms and conditions except as otherwise agreed between
the parties.
[Clause 1 amended by No. 19 of 2010
s. 51.]
If any condition set
out in subsection (1) of section 9 is not fulfilled solely because
the owner has failed to comply with the owner’s obligations under
subsection (2) of that section, the contract remains in force on the same
terms and conditions until the parties agree otherwise, but subject to the
provisions of clause 4.
[Clause 2 amended by No. 19 of 2010
s. 51.]
3 . Failure by builder and owner
If any condition set
out in subsection (1) of section 9 is not fulfilled and both the
owner and the builder have, or neither the owner nor the builder has, failed
to comply with their respective obligations under subsection (2) of that
section, the contract remains in force on the same terms and conditions until
the parties agree otherwise, but subject to the provisions of clause 4.
[Clause 3 amended by No. 19 of 2010
s. 51.]
4 . Rights of builder and owner
Where clause 2 or
3 or section 13(4)(c) applies —
(a) the
builder may by notice in writing to the owner —
(i)
increase the price stipulated in the contract by an
amount set out in the notice; and
(ii)
specify when any increased amount is payable, which must
be either —
(A) not later than 10 working days after
the notice is given; or
(B) at the time of a progress payment;
(b) if
the amount of an increase exceeds 5% of the price stipulated in the contract,
the owner may terminate the contract in accordance with section 19 within
10 working days after receipt of notice under paragraph (a); and
(c) if
the owner so terminates the contract, the owner is liable to compensate the
builder for the reasonable costs incurred by the builder up to the date of
termination.
[Clause 4 amended by No. 19 of 2010
s. 51.]
(1) If the owner
considers that the amount of a price increase notified under clause 4(a)
is excessive or unjustified, the owner may make a complaint under the Building
Services (Complaint Resolution and Administration) Act 2011 section 5(2).
(2) On a complaint
referred to in subclause (1) the builder is required to show that the
price has been increased to reflect actual increases in costs between the date
of the contract and the date of the notice under clause 4(a).
[(3) deleted]
[Clause 5 amended by No. 19 of 2010
s. 51; No. 16 of 2011 s. 126.]
[Schedule 1 amended by No. 57 of 1997
s. 73; No. 76 of 2000 s. 57 and 58; No. 37 of 2002 s. 20;
No. 19 of 2010 s. 4 and 51.]