Western Australian Consolidated Regulations[bl. 7 and 9(5)]
|
Description of fee |
Amount |
|---|---|
|
1. Non‑refundable account establishment fee
payable on the establishment or transfer of an account ................. |
|
|
2. Three phase residential
installation — (a) new
installation or replacement of single phase meter
................................................................. (b)
installation of subsidiary three phase meter (each installation)
............................................. |
|
|
3. Non‑refundable reconnection fee where
supply has been terminated for non‑payment of charges or for any other
lawful reason ............................................... |
|
|
4. Connection to standard public telephone
facility where supply not independently metered (per day) |
|
|
5. Temporary supply connection — | |
|
(a)
single phase (overhead) .................................... |
$300.00 |
|
(b)
three phase (overhead) ..................................... |
$600.00 |
|
6. Meter testing — | |
|
(a)
standard meter testing fee ................................. |
$156.55 |
|
(b)
reduced meter testing fee .................................. |
$144.00 |
|
7. Disconnection of overhead service leads
following unauthorised reconnection ..........................................
|
|
|
8. Meter reading where reading requested by
consumer.. |
$19.60 |
|
9. Supply of electricity to standard railway
crossing lights (per day)
............................................................ |
|
|
10. Overdue account notices
............................................ |
$4.65 |
|
11. Tariff R1 or R3 “time‑of‑use
meter” installation fee .. |
$809.60 |
[Schedule 4 amended in Gazette
26 Jun 2007 p. 3017; 30 Mar 2009 p. 982 and 994;
26 Mar 2010 p. 1138 and 1141-2; 24 Jun 2011
p. 2502.]
![]()