Western Australian Consolidated Regulations[r. 11(3)]
In addition to any matters outlined elsewhere in the regulations, an access
offer may include terms and conditions of the following kind:
(a)
details of each connection point;
(b) the
contract maximum demand (if any) in respect of each connection;
(c) if
more than one person is selling or purchasing the electricity transferred at
the connection, then the mechanism for determining how much of the electricity
transferred at that connection is sold or purchased by each of those persons;
(d) a
requirement that the user complies with the provisions of these regulations
and the Technical Code;
(e) any
metering arrangements and, if appropriate, a methodology to adjusting losses
where the point of metering is significantly different to the connection
point;
(f) the
payment conditions;
(g) if
the relevant connection is a new connection, then the date on which payments
in respect of the access services are to commence (whether or not the
connection is actually commissioned by that date);
(h) the
duration and termination conditions of the proposed access agreement;
(i)
terms and conditions in relation to the carrying out of
works to establish a connection;
(j)
testing and commissioning requirements;
(k)
agreed protocols for maintenance coordination;
(l)
provision, installation, operation and maintenance of automatic load shedding
facilities;
(m)
circumstances under which the terms of the resulting access agreement would
require renegotiation.