Western Australian Consolidated Regulations[Regulation 6.40]
Maximum periods of inspection of registered classified plant
|
Column 1 |
Column 2 |
Column 3 |
|---|---|---|
|
Item No. |
Description of plant |
Period |
|
1 |
Boilers categorized as hazard level A, B, C or D according to the criteria
identified in AS 3920: Part 1 |
2 years |
|
2 |
Pressure vessels categorized as hazard level A, B, C or D according to the
criteria identified in AS 3920: Part 1, with the exception
of — (a) air or gas receivers with a maximum
operating pressure of 210 kPa or less; (b) air or gas receivers that have a capacity not
exceeding 0.15 cubic metres; (c) pressure vessels fitted to mobile earthmoving
equipment; (d) pressure vessels fitted on a train; (e) gas cylinders covered by AS 2030; (f) serially produced vessels covered by
AS 2971; (g) pneumatic loaders of explosives. |
3 years |
|
3 |
Tower cranes |
Prior to use after each jump or one year whichever is less |
|
4 |
Lifts |
2 years |
|
5 |
Hoists, with platform movement in excess of 2.4 metres and designed to
lift people (Powered) |
2 years |
|
6 |
Boom‑type elevating work platforms |
2 years |
|
7 |
Gantry cranes with a safe working load greater than 5 tonnes or which are
designed to handle molten metal or dangerous goods |
4 years |
|
8 |
Bridge cranes with a safe working load greater than 10 tonnes or which are
designed to handle molten metal or dangerous goods |
4 years |
|
9 |
Vehicle hoists |
2 years |
|
10 |
Mobile cranes with a safe working load greater than 10 tonnes |
2 years. |