Western Australian Consolidated Regulations If a weighbridge does
not have a pit —
(a)
there must be a clearance of at least 150 mm under the lowest live part of the
platforms; and
(b) the
floor between load cell supports must be of concrete at least 75 mm thick and
must be effectively drained and kept free from any accumulation of water, mud
and debris; and
(c)
there must be in the same plane as, or lower than, the floor a clear space of
at least 1 m from the external edges of the frame of the weighbridge; and
(d) the
load cell footings must be individually and mutually stable.